Lincoln Street Pedestrian Improvements Project

Summer 2019

***Please use this link to report any issues during construction***

Pedestrian Improvements on Lincoln Street have been made possible by Complete Streets grant funding awarded to the Town by MassDOT. The project consists of installing a double-wide sidewalk along Lincoln Street to provide safe pedestrian and bike access between Thacher Street and Pierce Middle School via Brook Road. This project was bid in June 2019 and awared to Capone Bro's Inc. who will be starting work on the week of July 22nd, 2019 with a target completion date of August 21st, 2019. 

The plans for this project are attached to this form. Please check back here for updates throughout the project.

As a reminder to residents of Lincoln Street: parking will be prohibited between 7:00 AM and 5:00 PM Monday - Friday while construction is on-going.

For more information please contact the Engineering Department at (617) 898-4872 or via email at engadmin@townomilton.org.

Project Update 7/10/19

  • The Town's DPW will be on site today, and for the next few days, to relocate the fire hydrant at the corner of Thacher Street and Lincoln Street to the opposite side of the street in preparation of the roadway and sidewalk construction.

  • Due to changes in the geometry of the roadway at this location the new location of the hydrant will be slightly into the existing roadway, however this will only be a temporary condition until the changes have been made which will result in the hydrant ultimately being placed behind the new granite curbing.