The Contractor reconstructing parts of the path at Turner’s Pond will be installing the new path surfacing starting Thursday August 10.
The work should be completed in two-three days weather permitting.
Once the surfacing is completed, the binder material needs to cure for 3-4 days before it can be opened to foot traffic.
The lower path, leading to Glover School, will therefore be closed Thursday August 10 to Tuesday August 15.
The upper path will be closed Friday August 11 to the following Tuesday or Wednesday, depending on how curing goes.
Other parts of the park will be open at all times.
Please help protect the significant Town investment in this project and honor these guidelines.