The MWRA project will either resume on June 20th or June 23rd. They will be replacing a cement slab at Boulevard and Granite Avenue. The work is expected to last three to four weeks. The work will then cease temporarily and resume the beginning of September by the firehouse to tie in the existing lines. That work should last approximately three weeks. That would conclude Phase 1 of the project.
|